What should be prepared before the trommel screen commissioning?

Time:
10
02
2023
Author:ling
Views:405

What should be prepared before the trommel screen commissioning?

  1. After the components of the trommel screen are installed and passed the inspection, the test run can be carried out. Before the test run, check in detail that each component is installed correctly as shown in the drawing, that the fasteners are firm, and that there are no obstacles around the screen body that hinder the operation of the trommel screen;
  2. Put the rectangular inspection door in the open position, and rotate the screening cylinder by manual turning to observe whether the comb-shaped cleaning mechanism has jamming and friction, and if so, it can be adjusted by adjusting the bolt;
  3. Check that each bearing seat and gearbox should be well lubricated, and the oil level of the gearbox should be appropriate;
  4. The power connector should be firm and reliable, with good insulation and correct grounding.
Delivery site of obsolete garbage sorting equipment

Please get in touch with us

Meet your actual business needs.

keep
in touch
WhatsApp:
+8617513178882

Request a quote